These two four-storey hybrid buildings in the heart of Hirschthal in the canton of Aargau each contain 14 apartments. The elements of the curtain façade and the entire loft storey were constructed using our modular timber construction method, with solid stairwells and intermediate floors. The wooden and metal windows were already installed in the prefabricated elements at our factory in Eiken.
Services:
- Prefabricated timber construction
Client
Skyline Development GmbH
Obere Bühlstrasse 29
8700 Küssnacht
Switzerland
Obere Bühlstrasse 29
8700 Küssnacht
Switzerland
Architect
rd2b limited Architekturbüro
Hottingerstrasse 12
8032 Zurich
Switzerland
Hottingerstrasse 12
8032 Zurich
Switzerland
Area: | 720 m² |
Completion date: | 20.12.2013 |
Duration: | 12 months |
Construction cost: | CHF 0.86 million |
Project manager: | Hansueli Weber |